(Above) Ezam Khazeni, Senior Project Manager, Sully-Miller Contracting.

In preparation for the arrival of the Airbus A380 super jumbo, the world’s biggest-ever passenger plane, Sully-Miller Contracting completed in February most of a project that entailed the widening of existing runways and turns at Los Angeles International Airport (LAX). The eight-month project was preceded by months of complex and detailed planning in order to come up with an elaborate Quality Control plan, as well the general construction plan.

The Airbus A380 can seat up to 840 passengers on its two full decks, but will generally transport 555 passengers. At 928,300 pounds, it is the heaviest ever of any commercial airliner.

Sully-Miller isn’t new to the world of airport construction, and has worked at most southern California Airports. Their scope of work on this project included placing 5500 square yards of high-early strength concrete and 2700 square yards of regular 28-day strength concrete.

The $6.7 million contract called for an elaborate rotating three-day plan for removing the existing concrete, grading and placing the new concrete. All work on the runways was completed overnight in eight-hour shifts, and the runways had to be fit for use by 747s and smaller aircraft the following morning.

Each night the Sully-Miller crew would excavate a 25-foot by 75-foot by 21-inch deep section of the existing runway. After excavation, the crews would insert pre-fabricated plates measuring 10 feet by 30 feet that were double reinforced with I-beams. They had ten plates manufactured for the project. On night two, the crews would grade the first section in preparation for concrete placement the following night. The plate would then be replaced. On night three, the crews would pour concrete in the area prepped the night before, and start the process again by excavating the next area and moving the plates to cover this new section. The crews ended up pouring concrete every other night by following this pattern in conjunction with the paving plan.

(Below) SM crews pouring concrete, also providing sample to QC. You can see the Lighted X runway closure in the background.

Due to the stringent Federal Aviation Administration (FAA) specifications—including P501 mix concrete—it was imperative the Quality Control and Quality Assurance people be more involved in this project than they may be on other projects, Ezam explained. Sully-Miller had a full team of Quality Control people on the job on a daily basis. The elaborate Quality Control plan touched all phases of the project. The schedule was tied into the plan, as well as approval of all materials used on the project. All sub-contractors on the project were also tied into the plan.

“For example, the rebar cages were manufactured in Texas,” Ezam says. “We set up inspection of the cages at the manufacturer’s facility to ensure quality/approval of the product prior to shipping to the job.”

Sully-Miller hired Twining Labs to oversee the implementation of the quality plan on the job on a daily basis.

The biggest challenge on this project, according to Ezam, was to come up with a way to pour concrete every other night. Once they came up with the plan to use the plates, they had to make sure the plates would easily move from one hole to another each night, similar to a checkerboard pattern. They also constructed a movable platform on wheels that bridged over each hole so that the finishing crew could work on the concrete before it set up.

Ezam says the Sully-Miller changed the original phasing plan set forth in the contract to minimize impact to the airport operations. Doing the paving this way saved the airport money.

All the pours were by hand, placing 130 cubic yards of concrete each night. Sully-Miller had laser screeds and four to five concrete vibrators on hand each night. The crews also used excavators and rollers to prepare the sub-grade. Jim Copley, Sully-Miller’s Quality Control Director, played a key role on this project, as did Ron Salcido, Sully-Miller’s Chief Estimator.

Sully-Miller Contracting is a 70-year-old general contracting company. They do concrete and asphalt paving and underground work throughout southern California.

According to Ezam Khazeni, project manager for Sully-Miller, the high-early strength concrete they used on the runways never failed in strength.

The high-early concrete, which set up in a maximum time of a 1/2 hour, had four hours to cure each night to get the proper strength. Ezam says that prior to beginning the first pour, Sully-Miller poured a test strip on-site and tested it to assure proper strength.

The concrete vendor, Associated Ready Mix, had their own Quality Control representative on the job each night, as did all the other agencies involved.

“The concrete pours went well because of all the different people involved in the job each night,” Ezam explains.

In addition to the runways and turns, Sully-Miller had crews onsite working in closed areas 24 hours a day. The work they did in these areas was similar to that done in the night areas, but these areas were a safe distance from the aircraft so the work could proceed without having to open the areas every day for aircraft traffic. All together, Sully-Miller had 40 employees on the project.

 

 

 

 

 

 

 

(Above) SM crews pouring concrete and finishing the surface form on the Bridge. (Right) An excavator demolishing and loading a Super 10 Wheeler truck. (Below) After the crane completed seeting plates, a laborer cheks the alignment.

 

 

 

 

 

 

 

The company also includes two other companies: United Rock Products, which provides construction materials for the greater Los Angeles County area, and Blue Diamond Materials, which produces asphalt concrete for projects within a four county area in southern California. Sully-Miller’s corporate offices are in Anaheim, with a satellite office in Victorville.

Ezam thinks that one of the things that makes Sully-Miller stand out in the industry is the company’s commitment to handle all projects, including problems, in a professional manner.

“The people at Sully-Miller are good people,” he comments. “They handle project-related issues in a non-confrontational way.

“Safety and quality are our top two goals, ” Ezam says. “We’re doing our job if we’re taking care of these.”

For more information call 714-578-9600. Cc

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Right) SM crews pourig and finishing concrete on the LAX project. (Below) Rebar cages being delivered to the pour.

 

 

 

(Left) After the crane lifts and removes the plate, the breakers are ready to start. (Below) SM crews checking grade and setting up as the last plate is being removed. You can see the bridge in the background.

 

 

 

 

 

 

RETURN TO CONCRETE CONTRACTOR PROFILE DIRECTORY PAGE

 

 

 
 
 
   
   
   
   
   
   
   


 


 
    Contact the Webmaster